Build America, Buy America · Domestic content · Reshoring

Build America, Buy America: why electronics are the hard part of reshoring.

The Build America, Buy America Act asks federally funded projects to buy American-made products. For most materials that is a sourcing decision. For electronics it is a wall, and agencies keep writing waivers that name the same culprit: the printed circuit board. Here is what BABA requires, how it differs from the other Buy American rules, and what reshoring your boards actually takes, from a San Jose manufacturer that has assembled here since 1995.

By Tez AlamUpdated November 17, 202611 min read

Build America, Buy America (BABA) is a domestic-content preference that rides on top of federal infrastructure money. Passed inside the 2021 infrastructure law and spelled out in Office of Management and Budget guidance in 2023, it says a manufactured product bought with federal infrastructure dollars must be made in the United States and have more than 55% of its component cost come from US-made components. That second test is where electronics fail. Chips, displays and the boards that carry them are sourced globally, so agencies from the Energy Department to the EPA have granted nonavailability waivers that say, in almost identical words, that foreign suppliers dominate printed circuit boards. Reshoring is the way out, and it ran at about 247,000 announced US manufacturing jobs in 2025. Surface Art assembles printed circuit boards in San Jose and has since 1995. Here is how the rules fit together and where a domestic contract manufacturer helps.

Key facts as of November 2026. Sources are linked in each section below.
TopicThe factSource
Build America, Buy America ActDomestic-content preference for all federal financial assistance for infrastructure; enacted in the Infrastructure Investment and Jobs Act (November 2021); implemented by OMB in 2 CFR Part 184 (August 2023)OMB; Federal Register
The manufactured-products testMade in the United States, and the cost of US-manufactured components must exceed 55% of the cost of all componentsOMB BABA guidance
Where electronics fallBoards, and the products built on them, are "manufactured products," so they must clear the greater-than-55% testOMB BABA guidance
Why PCBs are the sticking pointAgencies issue nonavailability waivers stating that "foreign manufacturers dominate the supply of critical components — printed circuit boards (PCBs), LCDs, and metrology electronics"DOE; EPA waivers
Buy American Act (direct procurement)A separate, older rule for goods the government buys directly; domestic-content threshold is 65% through 2028, rising to 75% in 2029FAR 25.201
Reshoring momentumAbout 247,000 US manufacturing jobs announced through reshoring and foreign direct investment in 2025; computer and electronic products led the 2024 rankingsReshoring Initiative
Surface ArtAssembles in San Jose since 1995; registered with DDTC under ITAR; builds on US-fabricated bare boards for programs that require them; publishes monthly delivery and RMA data (99.81% on-time, 0.02% RMA, Jan–Jun 2026)Surface Art

What is Build America, Buy America?

Build America, Buy America is a domestic-content preference that applies to infrastructure projects paid for with federal financial assistance. Congress wrote it into the Infrastructure Investment and Jobs Act in November 2021, and the Office of Management and Budget implemented it in August 2023 by adding Part 184 to Title 2 of the Code of Federal Regulations. The point, in OMB's words, was to bring consistency to how federal agencies apply the rule.

BABA sorts everything bought for a project into three buckets, each with its own standard:

  • Iron and steel must have all manufacturing processes, from melting through coating, happen in the United States.
  • Construction materials must have all manufacturing processes happen in the United States.
  • Manufactured products must be manufactured in the United States, and the cost of their US-manufactured components must exceed 55% of the cost of all components.

Electronics live in that third bucket. A smart meter, a broadband terminal, a controller for a water plant, the circuit board inside any of them: all are manufactured products, so all must clear the greater-than-55% test. The component-cost math follows the Federal Acquisition Regulation's cost-of-components approach. Two things are easy to miss. First, BABA applies to grants, to non-federal projects funded in whole or in part with federal dollars, not to things the government buys for itself. Second, the preference is waivable: an agency can grant a public-interest, nonavailability or unreasonable-cost waiver, plus narrow exceptions for very small purchases. Hold onto that word, nonavailability. It is the whole story for boards.

How does BABA differ from the rest of the Buy American family?

"Buy American" is not one law. It is a family of rules with different thresholds, written for different buyers, and they get conflated constantly. If you are trying to reshore to satisfy a requirement, the first job is knowing which requirement you are under.

RuleApplies toDomestic-content standard for products
Build America, Buy America (BABA)Federally funded infrastructure (grants to states, utilities, localities)Made in the US and >55% US component cost
Buy American Act (1933)Goods the federal government buys directly65% US component cost through 2028, 75% from 2029
Buy America (transportation)FTA- and FHWA-funded transit and highway projectsHigher thresholds in places — e.g., 70% for transit rolling stock; 100% for iron and steel
DoD covered-PCB rule (10 U.S.C. 4873)Defense acquisition of printed circuit boardsNo covered boards, bare or assembled, from China, Russia, Iran or North Korea; statutory date January 1, 2027

The thresholds move, too. The Buy American Act's domestic-content bar rose to 65% for 2024 through 2028 and is scheduled to reach 75% in 2029, under the Federal Acquisition Regulation. And waivers have been getting harder to come by: in January 2025 the Federal Highway Administration ended a long-standing general waiver that had let manufactured products off the hook on federal-aid highway projects, pulling electronics on those projects squarely under the rule. In March 2026 the White House signed an executive order aimed at the accuracy of "Made in America" and country-of-origin claims, which raises the stakes on being able to prove, not just assert, where something was made. The direction is one way: more domestic content, fewer exemptions, more documentation. We cover the defense corner of this picture, the Pentagon's 2027 circuit board rule, in our post on American Dynamism and US PCB manufacturing.

Why do electronics break the 55% test?

Because the most expensive parts of a board, the semiconductors, are overwhelmingly made offshore, and they count toward the 55%. You can assemble a board in Ohio and still miss the threshold if the processor, memory, power management and RF front end on it were fabricated in Taiwan, Korea or China. Assembly is necessary for domestic content; on its own it is often not sufficient.

You do not have to take that from a manufacturer. Read the waivers. When agencies fund projects full of electronics, they repeatedly grant nonavailability waivers whose justification is the printed circuit board. The Department of Energy, funding advanced metering infrastructure for electric utilities, approved waivers in 2026 stating that "foreign manufacturers dominate the supply of critical components — printed circuit boards (PCBs), LCDs, and metrology electronics," so domestic compliance "is not achievable" for those meters. The EPA reached the same conclusion for water meters, noting the industry sources printed circuit boards and related electronics internationally. These are not loopholes; they are the government conceding that the domestic supply for board-level electronics is thin.

That thinness is upstream, in the bare board itself. The United States makes roughly 4% of the world's printed circuit boards, down from nearly a third around 2000, while China makes more than half. The number of North American fabricators fell from about 780 in 2000 to roughly 230 by 2020. We walk through that collapse, with the Bureau of Labor Statistics employment data behind it, in the American Dynamism post. The practical takeaway for BABA: the bare board and the chips are the hard dollars, and the assembler is the part of the chain that is clearly, documentably domestic.

Where does BABA actually land? Infrastructure that runs on boards.

BABA is often discussed as a steel-and-concrete rule. In practice, a large share of modern infrastructure is electronics, and that is where the compliance pain concentrates. If you build any of the following, your boards are inside BABA's reach:

  • Grid and utility electronics — smart meters and advanced metering infrastructure, which is exactly where DOE has been writing PCB waivers.
  • Broadband equipment — the $42.45 billion BEAD program applies BABA, and NTIA's guidance requires that certain equipment, including the assembly of its printed circuit boards, be done in the United States, with manufacturers certifying compliance to recipients. NTIA issued a limited nonavailability waiver in February 2024 for specific BEAD electronics, a tacit acknowledgment of the same board problem.
  • Water and wastewater controls — meters, SCADA and instrumentation funded through state revolving funds.
  • EV charging and energy storage — chargers and battery-management electronics funded through federal programs.
  • Transportation systems — signaling, tolling and transit electronics under the transportation Buy America rules.

Whether a finished product clears 55% depends on its whole bill of materials, which is a design and sourcing question, not something a contract manufacturer settles alone. But where the board is assembled, and where the bare board was fabricated, are facts a manufacturer controls and can certify. On a BABA project, those certifications are what a recipient needs in hand, and what an auditor will ask for.

What is driving the reshoring push?

Policy is one force; cost and risk are the others. All three now point the same way for electronics.

On policy, the domestic-content rules above are tightening on schedule and by executive action. On momentum, the Reshoring Initiative counted about 247,000 US manufacturing jobs announced through reshoring and foreign direct investment in 2025, roughly matching 2024 and bringing the running total past 2.3 million since 2010; computer and electronic products topped the category rankings in 2024. On cost and risk, tariffs have made offshore boards less of a bargain and more of a variable. Chinese-origin bare boards have carried a 25% Section 301 duty since 2018, and the targeted exclusions that spared some two- and four-layer boards were set to lapse in November 2026; the broader 2026 tariff picture has been unusually volatile, which is its own argument for a supply base you can predict. We would point readers to primary sources, USTR and CBP, for current rates, because they move.

None of this makes offshore sourcing disappear. It changes the arithmetic. When a federal rule requires domestic content, when tariffs erode the price gap, and when a single sanction can strand a supplier, keeping board work in the United States stops being a premium and starts being insurance.

What does reshoring your boards actually take?

Two things people conflate: moving assembly onshore, and moving fabrication onshore. They are different jobs, and most teams only need the first.

Assembly, placing and soldering components onto a board and testing the result, is the step most directly tied to domestic-content and country-of-origin questions, and it is the step a US contract manufacturer does every day. Fabrication, building the bare board itself, is the scarcer, more capital-intensive link; a new rigid-board fab runs an industry-estimated $250 million to $400 million, which is why so little of it is left here. For programs that require a domestically fabricated bare board, the move is to assemble in the US on a US-fabricated board; for programs that only need US assembly and documented origin, the assembler carries most of the weight.

Reshoring well is less about finding the cheapest domestic shop than about finding one that can answer the compliance questions and still ship on time. The questions worth asking any prospective partner:

Question to askWhy it matters
Where is the board assembled, and can you certify it?BABA and Buy America turn on where manufacturing happens; BEAD requires manufacturers to certify compliance in writing.
Where will my bare boards be fabricated?Country-of-origin rules, and the DoD 2027 circuit board rule, look at where the bare board was made, not only where it was assembled.
Can you document origin for every board?Waiver requests and compliance certifications need traceable, defensible origin records.
Are you registered with DDTC under ITAR?Manufacturing a defense article requires State Department registration, even for a shop that never exports.
Do you publish your delivery and quality performance?Reshoring only helps if the domestic shop actually delivers. Dated, published data beats an undated "99% on-time" claim.

Our NPI checklist covers what to send a manufacturer before the first board, and our ITAR assembly page covers the defense side in more depth.

Reshoring a board program and need to document domestic content? Talk to us about your next build.

Schedule a call →

Why is Surface Art a good option for teams that need to reshore?

Because the part of the chain that reshoring actually hinges on, US assembly with provable origin and a delivery record you can check, is the part we have done in one place since 1995.

We assemble every board in our San Jose facility. For programs that require it, we build on bare boards fabricated by US fabs; we source boards offshore only when a customer asks, and we document where each board was fabricated and assembled so the origin question has a paper answer. We are registered with DDTC under ITAR, which the rules require for defense articles, and we are certified to ISO 9001:2015 and ISO 13485. We build for satellite and drone programs and have experience working with Tier 1 and Tier 2 defense contractors, alongside aerospace, medical and industrial work, the same markets where domestic-content and country-of-origin questions come up.

We will also tell you where a manufacturer's certainty ends. We can certify where a board was assembled and fabricated; whether a finished product clears BABA's 55% depends on its whole bill of materials, including chips we do not make. We will not promise a compliance outcome that is not ours to promise. What we will do is give you an origin record that stands up and a schedule that holds.

On that last point, we publish our numbers. Most contract manufacturers advertise an undated on-time figure; we post our monthly on-time delivery and RMA rates and refresh them every six months. For January through June 2026 that was 99.81% on-time and a 0.02% RMA rate, with every return counted, not just confirmed workmanship failures. You can see the monthly breakdown on our homepage. We are one of very few contract manufacturers that publish actual delivery and quality data, and reshoring is precisely the moment that data earns its keep: moving a program onshore only pays off if the onshore shop ships.

Because domestic fabrication capacity is scarce, we are also exploring bringing bare-board fabrication in-house. We are exploring it, with no timeline announced; the American Dynamism post explains why that is hard and why we would rather say so than overpromise.

Frequently asked questions

What is the Build America, Buy America Act in one sentence?

It is a domestic-content preference requiring that iron, steel, manufactured products and construction materials bought with federal infrastructure funding be produced in the United States, with manufactured products needing more than 55% US component cost.

Does BABA apply to things the federal government buys directly?

No. BABA applies to federal financial assistance, grants that fund non-federal infrastructure projects. Direct federal purchases fall under the older Buy American Act, which has its own thresholds (65% now, rising to 75% in 2029).

Does assembling a board in the US make it BABA-compliant?

Not by itself. The product must be manufactured in the US and have more than 55% US component cost. US assembly helps with both but can fall short if the semiconductors and the bare board are imported. That is why agencies grant nonavailability waivers for board-heavy products.

Which infrastructure electronics are affected?

Smart meters and grid electronics, broadband equipment (the BEAD program applies BABA), water and wastewater controls, EV charging and storage, and transportation systems, among others.

Where are Surface Art's boards made?

We assemble every board in San Jose. For programs that need it, we build on bare boards fabricated by US fabs; we source bare boards offshore only when a customer asks, and we document origin either way.

Can Surface Art guarantee my product meets BABA?

We can certify where your board was assembled and fabricated and give you defensible origin records. Whether the finished product clears the 55% threshold depends on its full bill of materials, which is a design and sourcing decision beyond assembly.

Is Surface Art ITAR-registered?

Yes. We are registered with the Directorate of Defense Trade Controls under ITAR, and certified to ISO 9001:2015 and ISO 13485.

Sources

  1. OMB final guidance on Build America, Buy America, 2 CFR Part 184, Federal Register (August 23, 2023). govinfo.gov; OMB BABA Q&A (August 2023). whitehouse.gov (PDF)
  2. Analysis of the 55% manufactured-products standard: Akin Gump. akingump.com; Faegre Drinker. faegredrinker.com; Congressional Research Service. everycrsreport.com
  3. DOE nonavailability waivers citing printed circuit boards (advanced metering infrastructure, 2026). energy.gov (PDF); federal waiver registry. madeinamerica.gov
  4. NTIA Build America, Buy America requirements for the BEAD program, and limited nonavailability waiver. ntia.gov (PDF); Commerce BEAD FAQs (August 2026). commerce.gov (PDF); Wiley analysis. wiley.law
  5. Buy American Act domestic-content thresholds, FAR 25.201 (65% through 2028, 75% from 2029). acquisition.gov; FAR Buy American Act final rule (2022). federalregister.gov
  6. FHWA rescission of the manufactured-products general waiver (effective 2025); White House executive order on "Made in America" origin claims, Holland & Knight (March 2026). hklaw.com
  7. Reshoring Initiative 2025 data (about 247,000 jobs). manufacturing.net; Reshoring Initiative 2024 annual report (category rankings). reshorenow.org
  8. Section 301 duties on China-origin printed circuit boards and the 2026 tariff picture (industry summaries; verify current rates with USTR and CBP). ourpcb.com; octopart.com
  9. US share of world PCB output and fab-count decline: Commerce and Homeland Security ICT supply chain assessment (February 2022). dhs.gov (PDF); TPCA/ITRI global PCB data, I-Connect007 (2026). iconnect007.com
  10. New-fab cost estimate and defense circuit board rule context: PCBAA testimony to the US-China Economic and Security Review Commission (2025). uscc.gov (PDF); 10 U.S.C. 4873. law.cornell.edu
  11. ITAR registration, 22 CFR 122.1. law.cornell.edu

Facts are current as of November 2026. Tariff rates and waiver scope change often; check USTR, CBP and the agency BABA pages for the current position. We will update this post as the rules move and when we publish our next six months of delivery and RMA data.