Engineering guide · Reshoring

Moving PCB assembly from China to the US: a transfer guide.

Moving a board from a Chinese contract manufacturer to a US one is mostly a data and supply-chain project, not a manufacturing one. This guide covers what to collect before you leave, how to re-source the BOM, what happens to tooling, and how to cut over without a gap in supply.

Surface Art engineeringUpdated November 20269 min read

Key takeaways
  • Get the as-built package out of your current supplier first: board data, a BOM with real manufacturer part numbers, test programs and fixtures, and the quality history.
  • Expect to re-source parts. Components bought in China often come through local channels or the supplier's own stock, and need checking against US authorized distribution.
  • Decide early whether you're moving assembly only, or bare boards too. They're separate decisions with different costs and compliance effects.
  • Treat the first US build as an NPI build, with DFM review and first article inspection, and keep bridge stock until it passes.
  • Compare total landed cost, not unit price. Tariffs, freight, customs, inventory and quality escapes all count.

Why teams move

The reasons usually stack up rather than arrive one at a time:

  • Tariffs and customs. Section 301 tariffs have applied to many Chinese-origin goods since 2018, and import rules keep changing. Our physical AI post covers the de minimis suspension and the FCC rules on foreign-produced drones and robots.
  • Program requirements. Federally funded infrastructure falls under Build America, Buy America, defense programs face the 2027 DoD printed circuit board rule, and ITAR-controlled hardware has to be built by a registered US manufacturer.
  • Lead time and inventory. Ocean freight and customs add weeks, so teams carry more stock to cover the gap.
  • Engineering access. Revisions go faster when engineers can see the first board the day it's built, in the same time zone.
  • Customers asking. More buyers now ask where boards are built before they ask about price.

Decide what moves

"Reshoring" can mean three different scopes. Pick one before you request quotes, because it changes the package, the cost and what you can claim about origin.

ScopeWhat changesWhen it fits
Assembly onlyBoards are assembled and tested in the US; bare boards and some parts may still come from overseasThe usual first step. Covers most "built in the US" and ITAR needs
Assembly and bare boardsBare boards are also fabricated in the USPrograms that look at where the bare board was made, such as the 2027 DoD rule
Assembly, boards and componentsThe BOM is re-sourced toward domestic or allied content where possibleDomestic-content tests such as BABA, or a "Made in USA" goal
Most teams start with assembly only, then move bare boards when a program requires it.

Collect the transfer package

Ask your current supplier for everything below while the relationship is still good. Some of it may be theirs under your contract; most of it should be yours.

Board data

  • Gerber, ODB++ or IPC-2581 files at the exact revision in production, plus drill files, the fab drawing and the stackup.
  • The centroid (pick-and-place) file, with reference designator, X-Y, rotation and side for every placed part.
  • The assembly drawing, stating the workmanship standard and IPC class, plus any special processes such as conformal coating, potting, underfill or press-fit.

Bill of materials

  • The as-built BOM, with a manufacturer and part number on every line. If your supplier filled parts from its own stock, the BOM you have may list stock codes or generic values instead. Ask for what was actually placed.
  • Approved alternates already qualified, and any substitutions the supplier made without asking.

Test, programming and quality

  • Test procedures, test programs and fixture designs for in-circuit and functional test, and a clear answer on who owns the fixtures.
  • Firmware images and programming instructions for every programmable part.
  • Packaging, labeling and serialization requirements.
  • Quality history: the engineering change list, known defects, field returns, and a few known-good boards from the last lot to use as golden samples.

Our NPI checklist covers file formats, BOM structure and the centroid file in more detail.

Re-source the BOM

The BOM is where most transfers slip. Parts bought in China often come through local distributors, brokers or the supplier's own inventory, and some are Chinese domestic brands with little or no US distribution. Before the first US build, check every line for:

  • Authorized availability in the US, and lead time from authorized distribution.
  • Lifecycle status: active, not recommended for new designs, or end of life.
  • Packaging and minimums: reel, cut tape or tray, and minimum order quantities.
  • Alternates for parts that are single-source, long-lead or hard to buy here. Some domestic-brand parts will need a cross-reference or a footprint change.
  • Counterfeit exposure. Buying through authorized channels with traceable lots reduces it.

Parts with long lead times set the date of your first US build, so start this review before anything else.

Tooling, test and programming

  • Stencils are usually cut new by the new assembler from your paste-layer data. They're inexpensive.
  • Test fixtures can sometimes be shipped and reused if they fit the new supplier's equipment. Budget to rebuild them if they don't, or if your old supplier won't release them.
  • Test and programming software may be tied to the old supplier's setup. Get the source and procedures, not just the fixture.

Plan the cutover

Don't stop production in China until the first US lot passes. A typical sequence:

  1. Send the package and request quotes for the quantity breaks you need, plus annual volume.
  2. Answer the clarifying questions and confirm the assumptions behind the quote.
  3. DFM, DFT and BOM review before any parts are bought.
  4. Buy parts. The longest-lead parts set the schedule.
  5. First build and first article inspection, compared against your golden samples and drawing.
  6. Qualify the boards in your own system and test.
  7. Cut over, keeping bridge stock or a final China lot until the US supply is steady.

Compare total landed cost

A US assembly quote will often show a higher unit price than a Chinese one, especially for high-volume, labor-heavy boards. The gap is smallest for low-volume, high-mix work, where setup and engineering time dominate. Compare the full cost of each option:

  • Unit price, setup and NRE
  • Tariffs and duties at current rates, plus customs brokerage
  • Freight, and the inventory you carry to cover transit time
  • The cost of a quality escape found after a long shipment
  • Engineering time and travel for each revision

Tariff rates change often. Check them with your customs broker when you build the comparison.

Labels and origin claims

Moving assembly to the US does not by itself make a product "Made in USA". The Federal Trade Commission requires an unqualified "Made in USA" claim to mean that all or virtually all of the product is made in the US. A qualified claim such as "Assembled in USA" can fit when the product's principal assembly is done here and is substantial.

Buy America rules apply their own tests. Our BABA post explains the 55% domestic-content test for manufactured products. Get compliance advice before you put an origin claim on a product.

From the San Jose line

Surface Art assembles boards and complete systems in San Jose, California, and has since 1995. On a transfer, we:

  • Ask for the BOM as an Excel file with manufacturer part numbers, and pull the datasheet for every part for process review.
  • Send clarifying questions and state our assumptions before we quote, then quote the quantity breaks you need.
  • Run DFM, DFT and a BOM scrub for availability, lifecycle and cost before any parts are bought.
  • Build for programs that need it on bare boards fabricated by US fabs. Offshore fabrication is used only when a customer asks for it.
  • Document where boards were assembled and where bare boards were fabricated. Whether a finished product qualifies for a given claim depends on the rest of its bill of materials.

We also work with overseas partners on re-sourcing their supply chain toward BABA or FTC Made in USA requirements, with a dedicated project manager from our team. We're ITAR-registered, ISO 9001:2015 and ISO 13485 certified, and publish our on-time delivery (99.81%) and RMA rate (0.02%) for January–June 2026 on our homepage.

Frequently asked questions

Can I move only assembly and keep my bare boards in China?

Yes. Most transfers start that way. Move the bare boards later if a program, such as one under the 2027 DoD circuit board rule, looks at where the board was fabricated.

Will assembling in the US let me label my product "Made in USA"?

Not by itself. The FTC requires an unqualified "Made in USA" claim to mean all or virtually all of the product is made in the US. US assembly may support a qualified claim such as "Assembled in USA". Get compliance advice before making either.

How long does a transfer take?

Mostly as long as the longest-lead parts on the BOM, plus first article and your own qualification. Rebuilding test fixtures can add time. We'll tell you what drives the schedule during quoting.

What if my current supplier won't release the files?

Start from your own CAD data and BOM, plus a few known-good boards. Our DFM review will list anything still missing, such as test programs or the as-built part numbers.

Sources

  1. Federal Trade Commission, "Complying with the Made in USA Standard." www.ftc.gov
  2. 16 CFR Part 323, Made in USA Labeling Rule. www.ecfr.gov
  3. Office of the US Trade Representative, Section 301 investigation of China's technology transfer practices. ustr.gov

Start a transfer

Moving a board to the US? Send us the package.

Schedule a call →
Phone(408) 433-4700
Facility81 Bonaventura Dr, San Jose, CA